Phase I of Scott Hill Park & Sports Complex is nearing completion, with several key features now finished:
- The small, covered shelter and the maintenance building with restrooms are complete.
- The Phase I walking trail has been paved.
- The entrance road, entrance sidewalk, and auxiliary parking lot are complete.
Work is currently continuing on the bus/RV and soccer parking lots. Groundwork for soccer fields in Phase II of construction has begun.

Construction Phases
Phase 1:
- Entrance
- Trail head restroom
- Maintenance building/restrooms
- Parking lot #1
- Tot toys playground #1
- Covered shelter – 16’x 16′
- 1/3 of paved walking trail
- Multi-use field (natural) soccer & softball
- Covered event shelter – 40’x 30′
- 1/3 Landscaping
Phase 2:
- Soccer field parking (2 lots)
- 1/3 Paved walking trail
- 3 Artificial turf soccer fields
- Restroom Building
- 1/3 Landscaping
Phase 3:
- 2 Artifical baseball turf fields
- 2 Artificial softball turf fields
- Two-story concession stand/restrooms
- Tot toys playground 60′ x 40′
- Final 1/3 of paved walking trail
- Batting cages
- Bull pens
- Main parking lot
- Donor monument
- Large covered shelter (100’x 60′) with kitchen and storage
- Restroom building
- Roadway & sidewalk to Meriwether subdivision
- Final 1/3 landscaping